00:00:00.111 --> 00:00:02.813
It's really hard to make predictions, especially about the future.

2
00:00:03.093 --> 00:00:09.598
It might take 18 to 26 months to build, but new grid infrastructure, we're looking at five to ten years these days.

3
00:00:09.838 --> 00:00:13.881
A couple of months ago, we saw PJM drop 3.8 gigawatts of load.

4
00:00:13.921 --> 00:00:18.304
But a dose of realism when it comes to the physics of building infrastructure always helps.

5
00:00:23.375 --> 00:00:25.076
Can data centers lower your power bill?

6
00:00:25.116 --> 00:00:26.958
Can they really flex when the grid is stressed?

7
00:00:27.138 --> 00:00:31.381
Can utilities develop the grid infrastructure needed for tech that's built in 18 months?

8
00:00:31.642 --> 00:00:34.364
Everyone has a pitch, but few have the actual playbook.

9
00:00:34.464 --> 00:00:39.388
Today, we're joined by Chris Sturgill, grid modernization and clean energy partner at Scott Madden.

10
00:00:39.528 --> 00:00:44.052
And together, we pressure test the hype and give utility leaders the insights that they can actually use.

11
00:00:44.292 --> 00:00:46.974
And we want to give a shout out to Scott Madden for sponsoring this episode.

12
00:00:46.994 --> 00:00:48.975
We'll talk more about them as this conversation goes on.

13
00:00:49.255 --> 00:00:53.696
So Chris, utilities are getting flooded with huge data center load requests right now.

14
00:00:54.156 --> 00:01:01.119
Your data center playbook report mentions developers may show up before they have land, permits, financing, or even an end user.

15
00:01:01.659 --> 00:01:06.801
So in this environment, how do you separate serious projects from those that are just pure speculation?

16
00:01:06.881 --> 00:01:07.821
Thanks, Matt, and you're right.

17
00:01:08.101 --> 00:01:08.762
Utilities are,

18
00:01:10.222 --> 00:01:11.963
beset by all these applications.

19
00:01:12.003 --> 00:01:14.804
And in almost no time, the paradigm really flipped.

20
00:01:14.864 --> 00:01:23.808
So it went from utilities looking to go out and attract new load, because that's a way to show growth, to now being beset by too many applications to even review.

21
00:01:24.748 --> 00:01:36.273
And what utilities are doing to help with this is setting up structured intake processes to vet these projects, both from a commercial perspective and from an operational feasibility perspective.

22
00:01:37.033 --> 00:01:52.617
So in terms of what looks like a good project from a commercial perspective, those that are serious would have an identified project sponsor with a track record of performance, a financing plan with upfront deposits, and a willingness to commit financial resources as the project progresses.

23
00:01:52.857 --> 00:01:54.538
And then looking at it from the technical side,

24
00:01:55.178 --> 00:02:12.675
Those projects that have demonstrated site control, siting with proximity to existing resources, credible load estimates with options for phasing or ramping in power, a schedule with realistic timelines around things like siting, permitting, design, procurement, and all of that.

25
00:02:13.416 --> 00:02:17.099
and other infrastructure coordination when they're looking for water or fiber connections.

26
00:02:17.539 --> 00:02:17.840
Excellent.

27
00:02:17.860 --> 00:02:18.080
Yeah.

28
00:02:18.260 --> 00:02:28.648
And so if you're seeing from a developer, all those things, you know, obviously there's always the question of, you know, how much background is being put into it, how much they can come into fruition.

29
00:02:28.968 --> 00:02:39.837
I'm curious from your experience, are there almost under the radar, red flags or on the other side, green lights that planners can watch for across the lifecycle to really, you know,

30
00:02:40.237 --> 00:02:42.640
get under the hood about whether these things are coming or not.

31
00:02:42.840 --> 00:02:49.446
Yeah, I think the red flags would be those things that are kind of flying in the face of those commercially or technically serious projects.

32
00:02:49.466 --> 00:03:02.579
So it's it's kind of urgency without clarity around the schedule or it's opaqueness or lack of visibility into kind of who the project is, where it will be cited and that they demonstrated site control and all of those things.

33
00:03:02.639 --> 00:03:02.959
So it's

34
00:03:03.580 --> 00:03:10.102
So it's a bit of a diligence exercise in making sure that the developers have dotted their I's and crossed their T's.

35
00:03:10.402 --> 00:03:13.803
So for the utilities involved here, there's obviously a lot at stake.

36
00:03:13.863 --> 00:03:19.325
And I'm curious if you can talk about what are some of the biggest operational risks, financial risks that they're taking on.

37
00:03:20.205 --> 00:03:21.206
Yeah, thanks, Matt.

38
00:03:21.286 --> 00:03:23.288
And they are taking on both those risks.

39
00:03:23.368 --> 00:03:33.737
So on the financial side, it's the Goldilocks question of managing overbuild versus underbuild and missing the opportunity for growth.

40
00:03:34.137 --> 00:03:35.658
On the overbuild side...

41
00:03:36.519 --> 00:03:38.842
You're looking at things like stranded asset risk.

42
00:03:39.262 --> 00:03:44.408
And thus far, that hasn't really borne out because the markets have been so short of power.

43
00:03:45.549 --> 00:03:51.636
But at some point, if everyone keeps building, there may be a tipping point where there's an oversupply.

44
00:03:52.437 --> 00:03:55.200
And if you have counted on off takers of that,

45
00:03:56.301 --> 00:03:59.723
you may end up being long power when you didn't mean to be.

46
00:03:59.943 --> 00:04:11.508
There's also counterparty risk on the financial side, which is that we're seeing a lot of long-term contracts being set up, but if that entity isn't around, you can't sue nobody.

47
00:04:11.728 --> 00:04:19.452
So there's counterparty risk to manage as well, and that's why that commercial vetting that we talked about on the project intake becomes so key.

48
00:04:20.652 --> 00:04:27.736
And then there's also potential for cash flow crunches where utilities are having to commit to infrastructure projects up front.

49
00:04:27.997 --> 00:04:32.639
They get built and then you start collecting revenue from the customer once operational.

50
00:04:32.679 --> 00:04:34.100
And that can be years in the making.

51
00:04:34.180 --> 00:04:42.906
So we're seeing a lot of deposits and kayak and things like that that would help with the cash flow management.

52
00:04:43.233 --> 00:04:43.453
Yeah.

53
00:04:43.733 --> 00:04:52.896
Are there any real world cautionary tales that you can share with us where you've seen things go sideways, whether or not you can actually name who is involved?

54
00:04:53.116 --> 00:04:56.597
Not really on the financial side, but you mentioned operational risk as well.

55
00:04:56.637 --> 00:05:03.259
And I think that's where you've seen a lot in the in the press around data center trips offline.

56
00:05:03.279 --> 00:05:07.260
And then all of a sudden you're seeing gigawatt scale drops in load and.

57
00:05:08.460 --> 00:05:16.523
over frequency over voltage to, um, as a result in, in utilities and ISOs, RTOs and, um,

58
00:05:17.385 --> 00:05:19.626
NERC are looking at standards to address that.

59
00:05:19.666 --> 00:05:28.728
I think a couple months ago, we saw a PJM drop 3.8 gigawatts of load, and that's got a lot of people's attention.

60
00:05:29.308 --> 00:05:40.391
You mentioned sort of the Goldilocks situation where key to all of this is reliably and accurately, as much as possible, predicting future demand.

61
00:05:40.631 --> 00:05:43.172
And for the utility leaders, the cost of

62
00:05:43.832 --> 00:05:47.196
forecasting wrong is it can be astronomical.

63
00:05:47.276 --> 00:05:56.567
So how do how do leaders of the utilities balance that of the need for accurate forecasts with the inherent uncertainty that comes with them?

64
00:05:56.847 --> 00:06:01.533
Yeah, I really sympathize with utility forecasters because for years their their job was

65
00:06:02.623 --> 00:06:06.505
what it was last year, plus one or 2%, and it was pretty stable.

66
00:06:06.765 --> 00:06:12.247
And now it's kind of like the Yogi Berra quote of, it's really hard to make predictions, especially about the future.

67
00:06:12.427 --> 00:06:19.690
Because forecasting is at that front of the planning process, sharpening that process is top of mind.

68
00:06:20.990 --> 00:06:24.212
It goes back to that Goldilocks dilemma we were just talking about, and you're either...

69
00:06:24.972 --> 00:06:31.481
overbuilding with unused infrastructure or you're under building and then running into resource adequacy issues.

70
00:06:31.781 --> 00:06:37.628
And so there are a handful of kind of tactical steps that we've seen people taking to help with this.

71
00:06:38.554 --> 00:06:44.877
The first is around establishing stage-gated forecast categories that apply to the portfolio.

72
00:06:44.897 --> 00:06:55.883
So if a project is kind of just at the outset, has just been taken in, it really doesn't factor into the load forecast in the same way that a more mature project that is under construction would.

73
00:06:56.844 --> 00:07:02.407
And so you're almost qualifying the contribution to the forecast as projects mature.

74
00:07:04.100 --> 00:07:06.566
we're seeing more granular and more frequent forecasting.

75
00:07:06.606 --> 00:07:09.955
So if it wasn't an annual cycle, it might now be quarterly.

76
00:07:12.057 --> 00:07:26.982
and maintaining a consistent source of record or source of truth for the data around these projects so that forecasters and planners and the finance folks and the customer development groups are all kind of singing from the same sheet of music there.

77
00:07:27.882 --> 00:07:40.026
And then finally gets into a feedback loop of making sure that if we have assumed certain load shapes or certain phasing of consumption, that that matches what developers are doing in practice.

78
00:07:40.606 --> 00:07:53.275
One of the reasons that we're seeing data centers and energy really capture a lot of headlines is the intense focus on rates by everybody these days in the political sphere and at the utilities, customers themselves.

79
00:07:53.976 --> 00:07:57.538
And at least within the data center sphere, there's a popular narrative that...

80
00:08:00.320 --> 00:08:05.602
building these data centers can lower power bills by spreading fixed costs over huge sales.

81
00:08:06.122 --> 00:08:12.764
But in your report, you say that high load factor usage alone does not mean a project will necessarily lower rates.

82
00:08:13.364 --> 00:08:20.447
So if that's the case, what actually determines if regular rate payers benefit or get burned from these data centers being built in their backyard?

83
00:08:20.667 --> 00:08:28.950
It's a subject of much debate and really a way that you see the headlines impacting dinner time conversations that you didn't really expect where...

84
00:08:29.870 --> 00:08:38.094
Folks know that I work in the energy industry, so I get a lot of inbound questions about data centers and costs because that's the natural connection to draw.

85
00:08:38.954 --> 00:08:49.619
I think the correlation is there where data centers are a relatively new topic of conversation in the last five years and energy costs have gone up in the last five years.

86
00:08:49.659 --> 00:08:51.580
So kind of thus it must be so.

87
00:08:53.257 --> 00:09:12.197
And I think if you can take it on the simplest ends of this, which is if there was a big data center project coming on that was able to use kind of all existing available capacity, so no incremental costs, it would in fact spread the same fixed costs over more megawatt hours and

88
00:09:13.678 --> 00:09:15.379
put downward pressure on rates for ratepayers.

89
00:09:15.979 --> 00:09:18.520
But I think that capacity has been consumed.

90
00:09:18.560 --> 00:09:24.242
So now we're in the era of incremental infrastructure to support incremental demand.

91
00:09:24.642 --> 00:09:32.305
And the factors that go into that are kind of the headroom, the way the tariff is structured, the consumption pattern of the data center.

92
00:09:33.245 --> 00:09:36.286
and the phasing of how that load comes online.

93
00:09:36.986 --> 00:09:49.810
And that's where utility cost of service studies come in and the need to set up the tariffs in a way that cover all those costs that are directly attributable to the data center and then whatever they are consuming of

94
00:09:51.384 --> 00:09:52.385
Incremental capacity.

95
00:09:52.405 --> 00:10:03.654
And we've seen some interesting data center tariffs come out of Evergy and AEP that try to assign those incremental values and get that math right.

96
00:10:04.794 --> 00:10:12.020
I don't know that we will see the math play out on that in a definitive way for several more years because we're going to have a lot of data.

97
00:10:13.677 --> 00:10:23.191
new assets come on, are getting built, they're hitting the CapEx budgets, and will go into future rates.

98
00:10:23.251 --> 00:10:29.440
So it's almost too early to tell, but that's the balancing act on the math and where utilities are spending a lot of time.

99
00:10:30.101 --> 00:10:32.223
on cost of service studies and tariff design.

100
00:10:32.403 --> 00:10:45.217
And you mentioned, you know, too early to tell, but at the same time, all sorts of stakeholders are looking to build in protections now for consumers, whether that's politicians, consumer advocacy groups, regulators themselves.

101
00:10:46.358 --> 00:10:54.465
And we're seeing a lot of everything from voluntary pledges to mandates being debated, bans coming into certain localities.

102
00:10:55.305 --> 00:11:03.692
I'm curious what concrete protections you think that those consumer advocates should demand upfront to actually ensure that those benefits come to be.

103
00:11:03.892 --> 00:11:06.154
Yeah, it gets back into that tariff design.

104
00:11:06.214 --> 00:11:12.159
So you want provisions that deal with delayed projects or canceled projects,

105
00:11:12.879 --> 00:11:21.661
or where consumption doesn't match what was stated, and so you've overbuilt infrastructure for this project that's now getting spread elsewhere, and early termination, early exit.

106
00:11:21.801 --> 00:11:23.821
So you want to have protections against all of those.

107
00:11:24.341 --> 00:11:35.784
The cost of service piece of it wants to look at both the incremental, almost directly ascribed costs, but also what portion of existing capacity are these projects consuming that –

108
00:11:36.984 --> 00:11:39.948
that they should pay for, that they should, they're the causer of those costs.

109
00:11:39.968 --> 00:11:43.392
So those, and then transparency and reporting and tracking.

110
00:11:43.452 --> 00:11:47.657
So, you know, project said this, that was seven years ago, where are we now?

111
00:11:47.997 --> 00:11:55.546
And understanding if the benefits have, have borne out or if I think, as you said, the rate payers have been burned.

112
00:11:56.086 --> 00:12:01.709
And one of the other sources of consistent tension in this space is timeline.

113
00:12:01.769 --> 00:12:09.934
Data center, it might take 18 to 26 months to build, but new grid infrastructure, we're looking at 5 to 10 years these days.

114
00:12:10.014 --> 00:12:15.577
So how do utilities look to close that timeline gap when it's so wide?

115
00:12:15.777 --> 00:12:19.318
It is a wide gap, and it's probably not one they'll ever close fully.

116
00:12:19.459 --> 00:12:21.360
I think that the answer to...

117
00:12:22.240 --> 00:12:26.722
when would you like this power demand was, or when, and how much would you like this power demand is all of it.

118
00:12:26.802 --> 00:12:37.086
And two years ago, you know, if you think about all the steps we've been talking about so far around forecasting and planning and project vetting and contracting, all of that gets you to a point.

119
00:12:37.166 --> 00:12:43.609
And then you have to actually go design and procure all the material for and build the infrastructure to serve that.

120
00:12:44.409 --> 00:12:45.970
And, and that's non-trivial.

121
00:12:46.410 --> 00:12:46.510
Um,

122
00:12:48.055 --> 00:13:15.655
What we see utilities doing to try to close that gap is looking at things like standardized designs that mitigate challenges with kind of one-offs and a lot of back and forth on the design process between utility and developer, looking at breaking it out, breaking out the work and the capacity delivery in phases so that as they are able to build infrastructure and bring more power to bear, the data center can start ramping up its load.

123
00:13:17.316 --> 00:13:38.873
looking at contracting arrangements for long lead time equipment, sometimes polling, sometimes kind of strategic sourcing agreements, looking at addressing labor shortages, both on the design side and the build side with EPC relationships, and looking at kind of change control procedures so that

124
00:13:40.104 --> 00:13:50.740
As the design matures and if it changes, you can quickly determine whether or not that's going to result in a timeline shift because new equipment's needed or a new component has been added.

125
00:13:50.860 --> 00:13:53.043
So there's lots that go on there.

126
00:13:54.050 --> 00:13:59.251
And again, none of that probably brings you to a point of 18 months where it takes it for the data center.

127
00:13:59.791 --> 00:14:04.492
But I think that can be, it all helps.

128
00:14:04.652 --> 00:14:11.654
And then you're working on the relationship with the customer and helping them know what to expect at every point in the process.

129
00:14:11.674 --> 00:14:13.414
So they don't expect magic.

130
00:14:13.454 --> 00:14:16.175
They're expecting reasonable build of the project.

131
00:14:16.235 --> 00:14:26.237
Yeah, that's what I was going to ask is part of the onus on the tech companies who are wanting the data centers to have more realistic expectations and maybe meet those utilities halfway.

132
00:14:26.457 --> 00:14:26.997
I think so.

133
00:14:27.157 --> 00:14:33.618
They may get creative and decide that that's not working fast enough and they're going to look for kind of macro grids and building it themselves.

134
00:14:33.698 --> 00:14:36.678
And they've certainly got the balance sheets to do that.

135
00:14:36.779 --> 00:14:43.020
But a dose of realism when it comes to the physics of building infrastructure always helps.

136
00:14:43.340 --> 00:14:43.820
Yeah, yeah.

137
00:14:43.860 --> 00:14:44.840
Physics aren't flexible.

138
00:14:47.089 --> 00:14:58.015
The other story we often hear as kind of pushback to the data center criticism as ways that they can be good stewards of the grid comes from flexible load.

139
00:14:58.095 --> 00:15:08.222
The idea that as a data center can shift their compute power time-wise, they can run backup batteries, they can curtail completely if needed when the grid is strained.

140
00:15:09.042 --> 00:15:12.926
How much of that is actually real and being used today?

141
00:15:12.946 --> 00:15:16.309
And how much of it is maybe what we can call pitch deck optimism?

142
00:15:16.710 --> 00:15:19.432
Here in Raleigh, North Carolina, I'm just down the road from Duke University.

143
00:15:19.452 --> 00:15:21.875
I put out a really interesting study on this.

144
00:15:21.915 --> 00:15:27.980
And there are potentially gigawatts of kind of available capacity if you can start shifting around load.

145
00:15:28.761 --> 00:15:35.871
And I think that's attractive for kind of obvious reasons in terms of avoiding the cost and time of building all of that.

146
00:15:36.212 --> 00:15:38.535
But I so the idea is sound.

147
00:15:38.555 --> 00:15:39.216
I think the.

148
00:15:40.947 --> 00:15:59.236
to date it has largely been kind of a paper exercise and pitch deck optimism is as you might have said it certainly has drawn interest in groups trying to figure this out like EPRI's DC flex and and working consortiums I think one important thing to keep in mind here is the

149
00:16:02.437 --> 00:16:17.332
an operational time horizon, which is things like demand response, that utility operators have the purview and the mandate to kind of control things in the moment and call upon demand response resources or curtail loads if they need to.

150
00:16:18.273 --> 00:16:27.476
But that's very different than the planning time horizon where utility planners are saying, I know that this resource will be here as stated in the future.

151
00:16:27.996 --> 00:16:41.341
And that's where I think the longest gap is in terms of getting operational flexibility stood up in a meaningful way is that planners will probably not count on that kind of capacity until there's...

152
00:16:43.279 --> 00:16:50.645
some performance track record of those resources showing up in that way, that there are some contractual mechanisms to make sure they do or penalties if they don't.

153
00:16:51.526 --> 00:16:58.632
And that gets back to grid stability and grid safety and probably not something they're going to budge on too readily.

154
00:16:58.973 --> 00:17:03.036
And then the data center side of that is, well, I don't know how often you're going to call it.

155
00:17:03.156 --> 00:17:04.297
I don't know for how many hours.

156
00:17:04.498 --> 00:17:06.980
I've got a significant opportunity cost when you do.

157
00:17:08.621 --> 00:17:11.562
if I've got to disrupt my computational workloads.

158
00:17:11.642 --> 00:17:15.423
So I think both parties are pretty wary about that as a real solution.

159
00:17:15.683 --> 00:17:19.504
And it'll take some, I think, successful proof of concept to get there.

160
00:17:19.684 --> 00:17:20.384
Yeah, that makes sense.

161
00:17:20.444 --> 00:17:31.847
And you mentioned there's different time horizons, but I imagine there's also some variation in how applicable it is based on geographic region or the local grid mix or even the type of data center.

162
00:17:32.427 --> 00:17:32.927
It could.

163
00:17:33.047 --> 00:17:36.488
The type of data center and what kind of loads they are willing to shift or...

164
00:17:37.688 --> 00:17:44.072
or can't because it's a long training run kind of workload, that certainly plays into it.

165
00:17:44.832 --> 00:17:49.315
The ramp of your generation mix and how quickly you can ramp that up or slow it down.

166
00:17:49.635 --> 00:17:49.995
Excellent.

167
00:17:50.035 --> 00:17:54.418
So Chris, we want to end the conversation on an actionable point.

168
00:17:54.458 --> 00:18:03.943
So if you were in the C-suite, you're steering a utility through this wave over the next five years, what's the one biggest mistake you'd be trying to avoid right now?

169
00:18:04.323 --> 00:18:05.904
I think it's...

170
00:18:06.938 --> 00:18:08.679
locking into something prematurely.

171
00:18:08.739 --> 00:18:13.523
So the biggest thing right now is just these great cones of uncertainty and where things are going to go.

172
00:18:14.143 --> 00:18:29.774
And so I'd want to maintain kind of nimbleness in my processes, probably most of all, that link between the capital planning and budgeting forecast and the actual operational kind of infrastructure planning processes and making sure that

173
00:18:30.735 --> 00:18:32.196
I'm staying on top of my projects.

174
00:18:32.236 --> 00:18:37.940
I'm seeing what materializes and when and how quickly I'm able to build and respond.

175
00:18:38.340 --> 00:18:45.225
And then also, if things start to pull back, not being so far kind of out over the edge on that, that you get burned financially.

176
00:18:45.265 --> 00:18:50.289
It's a lot to juggle, but it sounds like it's, you know, the map is out there for how to do it.

177
00:18:51.449 --> 00:18:52.250
It's an exciting time.

178
00:18:52.270 --> 00:18:52.630
Thank you.

179
00:18:53.251 --> 00:18:54.011
It is, it is.

180
00:18:54.172 --> 00:18:55.553
And it's a critical time.

181
00:18:55.593 --> 00:18:59.536
Again, we're talking about this a lot now, but we know it's only going to ramp up.

182
00:18:59.596 --> 00:19:05.460
So we thank you for joining us to share your insights in this fast moving space today.

183
00:19:05.821 --> 00:19:06.041
Great.

184
00:19:06.201 --> 00:19:06.621
Thank you, Matt.

185
00:19:06.661 --> 00:19:07.202
Pleasure to be here.

186
00:19:07.522 --> 00:19:10.344
And thanks as well to Scott Madden for sponsoring today's episode.

187
00:19:10.424 --> 00:19:14.966
Scott Madden is a management consulting firm serving clients across the energy utility ecosystem.

188
00:19:15.547 --> 00:19:25.372
Areas of focus include transmission and distribution, the grid edge, generation, energy markets, rates and regulations, corporate sustainability, and corporate services.

189
00:19:25.812 --> 00:19:29.014
And thanks as well to our audience for joining us today on Power Perspectives.

190
00:19:29.274 --> 00:19:30.315
We will see you next time.